T1 - Hierarchy-based algorithms for minimizing makespan under precedence and communication constraints
AU - Kulkarni, Janardhan
AU - Li, Shi
AU - Tarnawski, Jakub
AU - Ye, Minwei
N1 - Publisher Copyright:
Copyright © 2020 by SIAM
PY - 2020
Y1 - 2020
N2 - We consider the classic problem of scheduling jobs with precedence constraints on a set of identical machines to minimize the makespan objective function. Understanding the exact approximability of the problem when the number of machines is a constant is a well-known question in scheduling theory. Indeed, an outstanding open problem from the classic book of Garey and Johnson [9] asks whether this problem is NP-hard even in the case of 3 machines and unit-length jobs. In a recent breakthrough, Levey and Rothvoss [24] gave a (1 + ∈)- approximation algorithm, which runs in nearly quasi-polynomial time, for the case when job have unit lengths. However, a substantially more difficult case where jobs have arbitrary processing lengths has remained open. We make progress on this more general problem. We show that there exists a (1+∈)-approximation algorithm (with similar running time as that of [24]) for the nonmigratory setting: when every job has to be scheduled entirely on a single machine, but within a machine the job need not be scheduled during consecutive time steps. Further, we also show that our algorithmic framework generalizes to another classic scenario where, along with the precedence constraints, the jobs also have communication delay constraints. Both of these fundamental problems are highly relevant to the practice of datacenter scheduling.
AB - We consider the classic problem of scheduling jobs with precedence constraints on a set of identical machines to minimize the makespan objective function. Understanding the exact approximability of the problem when the number of machines is a constant is a well-known question in scheduling theory. Indeed, an outstanding open problem from the classic book of Garey and Johnson [9] asks whether this problem is NP-hard even in the case of 3 machines and unit-length jobs. In a recent breakthrough, Levey and Rothvoss [24] gave a (1 + ∈)- approximation algorithm, which runs in nearly quasi-polynomial time, for the case when job have unit lengths. However, a substantially more difficult case where jobs have arbitrary processing lengths has remained open. We make progress on this more general problem. We show that there exists a (1+∈)-approximation algorithm (with similar running time as that of [24]) for the nonmigratory setting: when every job has to be scheduled entirely on a single machine, but within a machine the job need not be scheduled during consecutive time steps. Further, we also show that our algorithmic framework generalizes to another classic scenario where, along with the precedence constraints, the jobs also have communication delay constraints. Both of these fundamental problems are highly relevant to the practice of datacenter scheduling.
UR - https://www.scopus.com/pages/publications/85084058233
M3 - Conference contribution
AN - SCOPUS:85084058233
T3 - Proceedings of the Annual ACM-SIAM Symposium on Discrete Algorithms
SP - 2770
EP - 2789
BT - 31st Annual ACM-SIAM Symposium on Discrete Algorithms, SODA 2020
A2 - Chawla, Shuchi
PB - Association for Computing Machinery
T2 - 31st Annual ACM-SIAM Symposium on Discrete Algorithms, SODA 2020
Y2 - 5 January 2020 through 8 January 2020
ER -